Exterior masonry and roofing work are nearing completion. Plumbing, fire protection, mechanical, and electrical rough in work have been completed in all three wings.
Interior drywall installation, painting, and lay-in ceilings are nearing completion. The installation of windows, doors, flooring, carpeting, and mechanical equipment are in process. Site grading, landscaping, paving, and the installation of sidewalks are also continuing.
Realignment of Leesville Road adjacent the school property is currently in process.